During 2021 and 2022, INDEREN carried out the installation works of the biogas plant for the Maurienne project, located in Gourgançon, France.
In October 2021, INDEREN, subcontracted by the EnviTec Biogas engineering company and under its supervision, started the installation work of the buried polyethylene pipes of the plant. In addition, we accomplished various welding works of stainless steel pipes.
The INDEREN team completed the Maurienne project in May 2022.
Stainless Steel
Digester Assembly
Works carried out by INDEREN
The INDEREN team carried out the following works in the Maurienne biogas plant:
Platforms
- Assembly of different valves, pumps…
- Installation of the biogas pipes in the plant
- Installation of the substrate pipes in the plant
- Welding works of stainless steel pipes
- Assembly of the different platforms
Polyethylene Pipes
The photos about the Maurienne biogas plant in Gourgançon, France
Platforms
Digester Assembly
Stainless Steel
Platforms
At INDEREN we are pleased to be able to work on renewable energy projects that guarantee a more sustainable future.
We have extensive experience in the field of manufacturing, installation and commissioning of biogas plants and waste treatment plants. We also offer our customers container solutions: manufacturing of containers combining different systems according to the client’s needs (biogas, solar, industrial…). Contact us for more information.