In 2020, INDEREN participated in the construction of the biogas plant for the Quillet project, located in Étrépagny, France.
In November 2020, INDEREN, subcontracted by the EnviTec Biogas engineering company and under its supervision, started the installation work of the buried pipes of the plant. In addition, we installed all the aerial gas pipelines made of stainless steel for the gas channelling and the platforms of the tanks, the separator and the technical building.
The INDEREN team completed the Quillet project in March 2021.
Container Connections
Works of Tank Interior
Stainless Steel
Works carried out by INDEREN
The INDEREN team carried out the following works in the Quillet biogas plant:
Polyethylene Pipe
- Construction of aerial stainless steel gas pipelines
- Installation of the biogas pipes in the plant (aerial and buried)
- Installation of the substrate pipes in the plant (aerial and buried)
- Installation of pressure, temperature and height sensors in the tanks
Stainless Steel
- Installation of water pipes
- Installation of gas cooling
- Installation of simple, tandem, central and separator platforms
Container Connections
The video about the Quillet biogas plant located in Étrépagny, France
The photos about the Quillet biogas plant in Étrépagny, France
Polyethylene Pipe
Works of Tank Interior
Platforms
Gas Cooling
At INDEREN we are pleased to be able to work on renewable energy projects that guarantee a more sustainable future.
We have extensive experience in the field of manufacturing, installation and commissioning of biogas plants and waste treatment plants. We also offer our customers container solutions: manufacturing of containers combining different systems according to the client’s needs (biogas, solar, industrial…). Contact us for more information.