In 2021, INDEREN participated in the construction of the biogas plant for the AMV project, located in Feigneux, France.

In February 2021, INDEREN, subcontracted by the EnviTec Biogas engineering company and under its supervision, started the equipment assembly and installation work of the buried polyethylene pipes of the plant. In addition, we accomplished various welding works of stainless steel pipes.

The INDEREN team completed the AMV project in June 2021.

AMV Biogas Plant INDEREN Planta Biogás AMV INDEREN-Plataformas-01

Platforms

AMV Biogas Plant INDEREN Planta Biogás AMV INDEREN-Inoxidable-05

Stainless Steel

Works carried out by INDEREN

The INDEREN team carried out the following works in the AMV biogas plant:

AMV Biogas Plant INDEREN Planta Biogás AMV INDEREN-Plataformas-03

Platforms

  • Equipment assembly work in the tanks (agitators, wall bushings, heating system, peepholes…)
  • Assembly of different valves, pumps…
  • Installation of the biogas pipes in the plant
  • Installation of the substrate pipes in the plant
  • Welding works of stainless steel pipes
  • Design, manufacture and installation of platforms and access stairs necessary for the process in galvanized steel

Polyethylene Pipes

The photos about the AMV biogas plant in Feigneux, France

Assembly

Stainless Steel

Platforms

At INDEREN we are pleased to be able to work on renewable energy projects that guarantee a more sustainable future.

We have extensive experience in the field of manufacturing, installation and commissioning of biogas plants and waste treatment plants. We also offer our customers container solutions: manufacturing of containers combining different systems according to the client’s needs (biogas, solar, industrial…). Contact us for more information.

Share this article on Social Media Sites: