During the years 2022 and 2023, INDEREN participated in the construction of the biogas plant for the Belinchón project, located in Cuenca, Spain.

In May 2022, INDEREN, subcontracted by the ECOBIOGAS engineering company and under its supervision, started the equipment assembly and installation work of the buried polyethylene pipes of the plant. In addition, we accomplished various welding works of stainless steel pipes.

The INDEREN team completed the Belinchón project in March 2023.

Biogas Plant Belinchón INDEREN Planta Biogás Belinchón INDEREN-Tuberías PE aereas-04

Biogas Plant Belinchón INDEREN Planta Biogás Belinchón INDEREN-Tuberías PE aereas-02

Aerial Polyethylene Pipes

Biogas Plant Belinchón INDEREN Planta Biogás Belinchón INDEREN-Trabajos de soldadura de tuberías de acero inoxidable-02

Biogas Plant Belinchón INDEREN Planta Biogás Belinchón INDEREN-Trabajos de soldadura de tuberías de acero inoxidable-03

Works of Stainless Steel Pipes

Works carried out by INDEREN

The INDEREN team carried out the following works in the Belinchón biogas plant:

Assembly of Agitators, Valves and Equipment

  • Supply and installation of the heating network inside the tanks
  • Equipment assembly work in the tanks (agitators, wall bushings, heating system, peepholes…)
  • Assembly of different valves, pumps…
  • Supply and installation of biogas pipes in the plant
  • Supply and installation of substrate, feed, mixing, and condensate pipes in the plant

Biogas Plant Belinchón INDEREN Planta Biogás Belinchón INDEREN-Trabajos de soldadura de tuberías de acero inoxidable-01

Welding Works of Stainless Steel Pipes

  • Welding works of stainless steel pipes
  • Canalization works of polyethylene pipes both buried and aerial
  • Supply and installation of water pipes
  • Supply and installation of air pipes

Work Inside the Tanks

The photos about the Belinchón biogas plant in Cuenca, Spain

Biogas Plant Belinchón INDEREN Planta Biogás Belinchón INDEREN-Tuberías PE aereas-01

Biogas Plant Belinchón INDEREN Planta Biogás Belinchón INDEREN-Tuberías PE aereas-05

Aerial Polyethylene Pipes

Buried Polyethylene Pipes

Works of PPR Heating Network

At INDEREN we are pleased to be able to work on renewable energy projects that guarantee a more sustainable future.

We have extensive experience in the field of manufacturing, installation and commissioning of biogas plants and waste treatment plants. We also offer our customers container solutions: manufacturing of containers combining different systems according to the client’s needs (biogas, solar, industrial…). Contact us for more information.