In 2016, INDEREN carried out the installation works of the biogas plant for the Cler Verts project in Toulouse, France.
In 2016, INDEREN, subcontracted by the EnviTec Biogas engineering company and under its supervision, carried out the equipment assembly work in the tanks (peepholes, heating system, etc.). In addition, we installed the buried pipes of the plant and all the aerial stainless steel pipelines for the gas cooling inside the building. Currently, the biogas plant has a power of 637 kW and is located in Toulouse, Occitanie, France.
General view
Substrate downspout DN100
Installation works of the pipes
Works carried out by INDEREN
The INDEREN team carried out the following works in the Cler Verts biogas plant:
- Construction of aerial stainless steel gas pipelines
- Installation of the biogas pipes in the plant (aerial and buried)
- Installation of the substrate pipes in the plant (aerial and buried)
- Installation of the hot water pipes in the plant (aerial and buried, pre-insulated)
- Installation of pressure, temperature and height sensors in the tanks
Installation works of the pipes
- Installation of water pipes
- Installation of solid separator with its necessary pipes
- Installation of gas cooling
- Supply and installation of the CHP exhaust gas pipes
- Supply and installation of the sanitation system pipes
Polyethylene pipe work
The benefits of the biomethanization of the biogas plant in Toulouse, Occitanie, France
- The electricity generated will be enough to supply more than 900 families, having an annual electrical power production of 5070 MWh.
- The annual processing capacity of the plant is 18,000 tons of organic wastes. In addition, the digestate is obtained as fertilizer.
- Thermal energy is also generated, which will be used to achieve the anaerobic digestion and biomass drying.
- A variety of sources are used as raw material:
- Wood residues
- Legumes
- Supermarket organic waste
- 50 restaurants and 35 large supermarkets in the Toulouse region will contribute their organic waste to this methanation plant.
The photos about the biogas plant in Toulouse, Occitanie, France
General view
Installation works of the pipes
At INDEREN we are pleased to be able to work on renewable energy projects that guarantee a more sustainable future.
We have extensive experience in the field of manufacturing, installation and commissioning of biogas plants and waste treatment plants. We also offer our customers container solutions: manufacturing of containers combining different systems according to the client’s needs (biogas, solar, industrial…). Contact us for more information.