In 2023, INDEREN participated in the construction of the biogas plant for the Bioenergaz project, located in Argentré-du-Plessis, France.
In December 2022, INDEREN, subcontracted by the EnviTec Biogas engineering company and under its supervision, started the equipment assembly and installation work of the buried polyethylene pipes of the plant. In addition, we accomplished various welding works of stainless steel pipes.
The INDEREN team completed the Bioenergaz project in June 2023.
Stainless Steel Pipes
Works carried out by INDEREN
The INDEREN team carried out the following works in the Bioenergaz biogas plant:
Buried Polyethylene Pipes
- Equipment assembly work in the tanks (agitators, wall bushings, heating system, peepholes…)
- Assembly of different valves, pumps…
- Installation of the biogas pipes in the plant
- Installation of the substrate pipes in the plant
- Welding works of stainless steel pipes
- Design and manufacture of agitator covers and sliding gate
Manufacture of Gate and Agitator Covers
The photos about the Bioenergaz biogas plant in Argentré-du-Plessis, France
Installation of the Inside of the Tanks
Stainless Steel Pipes
At INDEREN we are pleased to be able to work on renewable energy projects that guarantee a more sustainable future.
We have extensive experience in the field of manufacturing, installation and commissioning of biogas plants and waste treatment plants. We also offer our customers container solutions: manufacturing of containers combining different systems according to the client’s needs (biogas, solar, industrial…). Contact us for more information.